Post by nienori on Jul 27, 2017 5:03:39 GMT
I would like to straighten and re-allocate the roads (Highways) on my deed, so Elfin suggested I make a post for you to review. If my proposals are not acceptable, please let me know if/what I need to tweak, or just tell me no so I can redesign the general layout of my buildings to work with the current road layout.
Edit to add: Location and current infrastructure: andistyr.github.io/wu-map/#451_1624
prntscr.com/g0tbx3
Steps are listed below picture.
1) Construct main E-W road, 5 tiles wide (2 slate brick, 1 grass* median, 2 slate brick). (In the spirit of complete transparency, construction on this road has already been started, at the junction of 1 and 5, before I found out that I should consult with Engineer about this.)
2) Construct main N-S road, 5 tiles wide (2 slate brick, 1 grass* median, 2 slate brick).
3) Construct secondary E-W road, remove nearest white road running parallel.
4) Construct secondary E-W road, remove parallel white road to the south. (This step must wait until inactive deeds are removed and area can be deeded.)
5) Construct secondary N-S road.
6) Construct main E-W road from tunnel to deed. (This step must wait until Grand Haven buildings have decayed and area is deeded.)
6a) Construct tunnel to link road to main N-S tunnel.
7) Indicated road replacement is extremely prospective at this point in time, depending on multiple factors. It is included in the plan for completeness.
Please let me know if you have any questions. I would be happy to talk this over with you and answer any questions or adjust as needed. Thank you!
Edit to add: Location and current infrastructure: andistyr.github.io/wu-map/#451_1624
prntscr.com/g0tbx3
Steps are listed below picture.
1) Construct main E-W road, 5 tiles wide (2 slate brick, 1 grass* median, 2 slate brick). (In the spirit of complete transparency, construction on this road has already been started, at the junction of 1 and 5, before I found out that I should consult with Engineer about this.)
2) Construct main N-S road, 5 tiles wide (2 slate brick, 1 grass* median, 2 slate brick).
3) Construct secondary E-W road, remove nearest white road running parallel.
4) Construct secondary E-W road, remove parallel white road to the south. (This step must wait until inactive deeds are removed and area can be deeded.)
5) Construct secondary N-S road.
6) Construct main E-W road from tunnel to deed. (This step must wait until Grand Haven buildings have decayed and area is deeded.)
6a) Construct tunnel to link road to main N-S tunnel.
7) Indicated road replacement is extremely prospective at this point in time, depending on multiple factors. It is included in the plan for completeness.
Please let me know if you have any questions. I would be happy to talk this over with you and answer any questions or adjust as needed. Thank you!